Gauhati High Court seeks contractor’s assurance on machinery, manpower and completion of delayed NH-29 Kohima–Jessami road by March 2027
DIMAPUR — With work on Package-II of the two-lane NH-29 Kohima–Jessami road progressing by less than 2% over the past month, the Gauhati High Court’s Kohima Bench on Wednesday directed the contractor to categorically state what steps it has taken with regard to the deployment of sufficient machinery and manpower at the project site, and indicate whether it can achieve completion by March 1, 2027.
Allowing Ratna Infrastructure Projects Pvt. Ltd. until November 25 to file its response, a division bench of Justice Robin Phukan and Justice Yarenjungla Longkumer issued the direction after considering affidavits from the Authority Engineer and the National Highways and Infrastructure Development Corporation Ltd. (NHIDCL) raising concerns over slow progress of the work and inadequate mobilisation of resources.
Figures placed before the court showed physical progress on the 21.90-km stretch stood at approximately 46.98% and financial progress at 45.55% up to October 2026, compared to 45.11% physical and 43.63% financial progress reported at the previous hearing on September 30. Despite repeated directions to mobilise adequate machinery, manpower and materials, progress achieved during the preceding month was less than 2%, the Authority Engineer stated.
Also read: RIPPL sets May 2027 deadline for NH-29 project completion
Gauhati High Court directs engineer to explain delay on Kohima-Jessami road project
Tracing the project’s timeline, the Authority Engineer’s affidavit recorded that the first contractor had been terminated when physical progress stood at 58.08% and financial progress at 54.08%. After the balance work was awarded to Ratna Infrastructure Projects through a letter of award dated October 10, 2023, the firm achieved physical progress of only about 4.70% between the appointed date and January 2025, a period of approximately one year.
Although an extension of time up to March 1, 2027 was granted via a letter dated September 18, 2026, the Authority Engineer stated that the contractor had repeatedly been directed to expedite the work within the approved extended completion period.
In its separate affidavit filed on Wednesday, NHIDCL stated that several notices had been issued to the contractor over its “continuous failure to maintain the required rate of progress” in accordance with the approved construction programme and contractual milestones, adding that the firm had failed to mobilise adequate resources at the project site till date.
The court is hearing a public interest litigation filed by the Chakhesang Public Organisation and another petitioner. At the previous hearing on September 30, the bench had directed the Authority Engineer to file an affidavit explaining the reasons for the delay and to remain personally present.
The matter has been listed for November 25, with the Authority Engineer directed to remain present on the next date.