- AIZAWL — Railway
Ministry is planning to extend the under-construction Bairabi-Sairang railway
line up to the India-Myanmar border, Mizoram’s Rajya Sabha member K. Vanlalvena
said on Tuesday.
-
- Mizoram’s Aizawl would be the fourth capital city in the
northeast region to be linked by a railway network within four to five months
after the completion of the 51.38 km Bairabi-Sairang new broad gauge line
project.
-
- The Northeast Frontier Railway (NFR) is laying the new broad
gauge line between Bairabi near Assam’s Hailakandi district and Sairang, near
Aizawl, at a cost of over Rs 8,215 crore.
-
- Vanlalvena, who on Monday inspected the Sairang railway
station site, on Tuesday said that the Railway ministry is planning to extend
the railway line up to Zochachhuah, a village on the India-Myanmar border.
Also read: Northeast Frontier Railway makes milestone achievements last fiscal year
-
- “Preliminary surveys are now being done to extend the
railway line up to the Myanmar border. It would significantly benefit Mizoram
once it’s operationalised. Government’s plan to further extend the railway
network beyond Sairang, cutting across southern Mizoram to Zochachhuah near the
Myanmar border, potentially opening doors for enhanced cross-border trade and
regional integration,” the Rajya Sabha member told IANS.
-
- The bordering Zochachhuah village falls under the Lawngtlai
district, which shares borders with Myanmar.
-
- The MP expressed satisfaction over the progress made on the
Bairabi–Sairang railway project, saying that of the estimated cost of Rs 8,215
crore for the project, Rs 7,714 crore has already been spent.
-
- “I consistently advocated for the railway project in the
Parliament. Centre’s plan to extend the railway line to the Myanmar border
would be beneficial for the entire northeastern region,” he pointed out.
-
- However, the tragic collapse of the steel girder bridge at
Kurung - the tallest along the under-construction railway route on August 23
last year, had set back the timeline by almost a year. The disastrous accident
claimed 23 lives of railway workers. NFR's General Manager, Construction,
-
- Meanwhile, Arun Kumar Chaudhary recently inspected the
ongoing Bairabi-Sairang railway project. Accompanied by senior railway
officials from the NFR headquarters at Maligaon near Guwahati, Chaudhury
inspected the worksite of the ongoing new line project, which includes
inspection of the construction of Kawnpui and Mualkhang station, Sairang
station yard, construction of bridges and tunnelling works in the project.
-
- NFR’s Chief Public Relations Officer (CPRO) Kapinjal Kishore
Sharma said that the Bairabi-Sairang new railway line project connecting Aizawl
in Mizoram with the rest of the country is at an advanced completion stage.
-
- This new line project is divided into four sections --
Bairabi-Hortoki, Hortoki-Kawnpui, Kawnpui-Mualkhang and Mualkhang-Sairang.
-
- The Bairabi-Hortoki section was commissioned in July last
year.
-
- The NFR is making all efforts to fulfil its commitment to
commission the project at the earliest, the CPRO said.