Jalukie Pumling Youth Organisation flags delays in road projects and poor maintenance of NH-129A, citing commuter safety concerns
DIMAPUR — The Jalukie Pumling Youth Organisation (JPYO) has raised concerns over delays in two ongoing road projects and alleged lapses in the maintenance of NH-129A, citing inconvenience to commuters and risks to pedestrian safety.
In a press release, the organisation expressed dissatisfaction with the progress of the PMGSY road connecting Jalukie and Kamdi Bazaar, saying that work remained unsatisfactory despite assurances given by the department concerned at a meeting on August 13.
It stated that a joint inspection promised during the meeting had also not been conducted and urged the department to expedite the work and fulfil its commitment.
The organisation also flagged slow progress on the SASCI road project between Jalukie Town Square and Catholic Church Junction. With the dry season setting in, excessive dust and unfinished stretches have caused hardship to commuters and pedestrians, it stated, adding that the road condition had contributed to accidents.
Also read: Youth body urges faster completion of NH-129A project in Jalukie
JPYO seeks urgent repair of PMGSY road in Jalukie as monsoon worsens conditions
The JPYO called on the department and executing agency to speed up construction and complete the project within the stipulated timeframe. It warned that it might intervene and halt the work if progress remained unsatisfactory or the deadline was not met.
On NH-129A Package-II, the organisation alleged inadequate maintenance, including failure to clear overgrown vegetation along road shoulders and pedestrian pathways. It added that pedestrians were being forced to use the main carriageway, exposing themselves to the risk of accidents.
It further pointed to incomplete installation of solar-powered streetlights, stating that lights had been installed on only one side of the Jalukie B Village stretch, while the Jalukie–Pungchi stretch remained without the facility.
It demanded installation of lights on both sides of the two stretches, along with immediate corrective measures to address the maintenance concerns.