Foundation stone for Dmp-Zubza rail link to be laid today

1
By EMN Updated: Aug 01, 2016 1:11 am

DIMAPUR, JULY 31 : As reported earlier, union minister of Railways, Suresh Prabhakar Prabhu would lay the foundation stone for the Dhansiri (Dimapur) – Zubza railroad on Monday at Dimapur railway station. The project was first sanctioned by the Railway Board as an 88-km long new broad gauge line in 2007-08.

Later, it was stretched to 90.50 km long after the alignment was modified to take the route from Dhansiri to Zubza through Sukhovi. The project was also declared as a National Project in 2007. On Sunday, the Northeast Frontier Railways (NFR) released some details about the project.
“The new line will take off from the existing rail head at Dhansiri railway station in Karbi Anglong district, 19 km short of Dimapur, and reach Zubza which is 16 km short of Kohima,” the NFR informed. Due to “very steep gradient” beyond Zubza, it stated, the railway line has been terminated short of Kohima, at Zubza.

The project would be executed in three separate phases. The first phase will cover construction 16 km stretch between Dhansiri and Sukhovi. The next phase would involve 30 km construction between Sukhovi and Khaibong. The final stretch would be between Khaibong and Zubza that covers a distance of 45 km.

“While the first phase of the project is targeted for completion by December 2018, the second phase is targeted for completion by December 2019 and the entire project by March 2020,” it informed.

 

SALIENT FEATURES OF THE PROJECT

SN Item Scope
1 Length 90.5 km
2 Tunnels 9 nos.
3 Total length of tunnels 21 km
4 Number of tall bridges 5 nos.
5 Major bridges 24 nos.
6 Minor bridges 89 nos.
7 Total length of bridges 4,438 km
8 New stations 7 nos.
9 Ruling gradient 1 in 80
10 Number of stations 8 nos. (Dhansiri, Dhansiripar, Sukhovi, Molvom, Khaibung, Chephema, Khabvuma, Zubza)
11 Total land required 940.5 hectare

 

FINANCIAL DETAILS

Year of sanction 2007-2008
Length 90.5 Km
Sanctioned cost Rs 2315.30 Cr
Expenditure up to 31.03.2016 Rs 145.45 Cr
Fund allocation for FY 2016-17 Rs 350 Cr
Expenditure in 2016-17 up to June 2016 Rs 2.6 Cr
Cumulative financial progress up to June 2016 6.4%